Plan and manage budget and resources
Plan and manage budget and resources
What you will learn
- Distinguish resource leveling from resource smoothing.
- Identify which of the two can extend the critical path and which cannot.
- Name the three common estimating techniques (analogous, parametric, bottom-up).
- Choose the most fitting estimating technique based on available historical data and level of detail.
When one resource is assigned to two tasks at the same time, there are two conflict-resolution tools many people confuse: resource leveling and resource smoothing. Both reschedule tasks around resource constraints, but the core difference between them is their effect on the project's end date.
Resource leveling vs. resource smoothing
| Resource Leveling | Resource Smoothing | |
|---|---|---|
| Effect on the critical path | Can extend the critical path and the project's end date | Doesn't change the critical path — works only within available float |
| When it's used | When resolving the resource conflict is a higher priority than keeping the original end date | When the project's end date is absolutely non-negotiable |
Three common estimating techniques
| Analogous Estimating | Estimating by analogy to a similar past project — fast but less accurate, fitting for early stages with limited data. |
|---|---|
| Parametric Estimating | Estimating using a statistical relationship between two variables (like cost per square meter × area) — more accurate than analogous when reliable data exists. |
| Bottom-Up Estimating | Estimating each small work package individually then aggregating — usually the most accurate, but slowest, and needs a fully detailed WBS. |
What matters on the exam
- A question stating the project's end date must not change points to resource smoothing, not leveling.
- Bottom-up is usually the most accurate but takes the longest and needs the most detail — don't assume it's always the default right answer regardless of project stage.
Leveling and smoothing aren't synonyms
A common trap: treating "resource leveling" and "resource smoothing" as interchangeable terms because both address resource conflicts. But leveling is willing to sacrifice the end date to resolve the conflict, while smoothing refuses to and works only within existing float.
Quick check
Answer in your head first, then reveal.
Which tool can extend the project's end date?Reveal the answer
Resource Leveling.
Which of the three estimating techniques is fastest but least accurate?Reveal the answer
Analogous Estimating.
Which estimating technique needs a fully detailed WBS?Reveal the answer
Bottom-Up Estimating.