Objective 2.15Process· 1 min read

Manage project issues

Manage project issues

What you will learn

  • Distinguish a risk from an issue, both in definition and handling.
  • Name the essential elements of an effective issue log.
  • Describe what happens when a negative risk actually materializes.
  • Identify when a delayed issue needs escalation rather than waiting.

Many confuse risk and issue because both threaten the project. The difference is critical: a risk is an uncertain possibility that hasn't happened yet, an issue is something that has actually happened now and needs immediate handling — and when a negative risk materializes, it effectively becomes an issue.

Risk vs. issue

RiskIssue
TimingAn uncertain future eventSomething that has actually happened now
Tracking toolThe Risk RegisterThe Issue Log

Managing an issue from logging to closure

  1. Log it

    A clear description, an owner, and a target resolution date.

  2. Follow up

    Regularly check against the target date, not passive waiting.

  3. Escalate when needed

    Especially with repeated delay or critical-path impact.

  4. Close and document

    For lessons-learned purposes in future projects.

What matters on the exam

  • When a negative risk materializes, it's logged in the issue log as an actual issue, while its historical documentation stays in the risk register.
  • Repeatedly missing the target resolution date, combined with critical-path impact, clearly signals a need to escalate and review the approach.

Risk and issue aren't synonyms

A common trap in question wording: using "risk" and "issue" interchangeably. A risk is a possibility that hasn't occurred yet; an issue is a present reality — the distinction determines which log to use and what kind of response fits.

Quick check

Answer in your head first, then reveal.

  1. What's the core difference between a risk and an issue?Reveal the answer

    A risk is an uncertain future possibility; an issue is something that has actually happened now.

  2. What should the issue log include?Reveal the answer

    The issue description, the owner responsible, and a target resolution date.

  3. What happens when a negative risk materializes?Reveal the answer

    It effectively becomes an issue, logged in the issue log and needing immediate handling.